Projects / Northern Forge

Northern Forge

A 125 MW behind-the-meter natural gas generation facility feeding an on-site compute campus. First power roughly six months from publication; Phase I energizing Q4 2026.

Capacity

125 MW

Phase I online

Q4 2026

Phase I cost

<$32/MWh

Site

~95 acres

OVERVIEW

First power in months, not years.

Northern Forge is a behind-the-meter gas-to-compute campus in Alberta — 125 MW of dedicated generation feeding compute load on the same site, under one sponsor. Phase I (30 MW) energizes Q4 2026, roughly six months from publication.

Primary engine secured (9.8 MW reciprocating, owned outright, OEM-warrantable). 10-year firm gas supply under LOI with a major midstream counterparty; dedicated 6-inch gas pipeline under LOI with a major midstream operator, sized for the full 125 MW build. AESO grid interconnect targeted for 2028 as Year-2 redundancy and secondary revenue.

SPECIFICATIONS

Project specifications.

Generation

125 MW behind-the-meter natural gas generation. Primary engine secured (9.8 MW reciprocating), owned outright, OEM-warrantable.

Configuration

Behind-the-meter — generation physically tethered to on-site compute load.

Location

Alberta, Canada.

Site

Crown lease accepted for the power plant footprint; expansion parcels totaling ~95 acres under application within 1 km of the site.

Gas Supply

10-year firm gas supply under LOI with a major midstream counterparty.

Gas Delivery

Dedicated 6-inch gas pipeline under LOI with a major midstream operator, sized for the full 125 MW build.

Grid Optionality

AESO grid interconnect targeted for 2028 as Year-2 redundancy and secondary revenue.

Permits

Permits largely in hand.

Energization

Phase I (30 MW) Q4 2026 — first power roughly six months from publication.

Cost economics

Below $32/MWh in Phase I.
Below $30/MWh long-term.

Northern Forge's economics sit comparably to Black Bear's on a behind-the-meter delivery basis, with the same AECO-hub gas advantage and the same Alberta climate / PUE advantage. Phase I starts below $32/MWh; the long-term steady-state runs below $30/MWh.

Behind-the-meter delivery bypasses AESO non-energy charges, transmission losses, and most regulated tariffs. The same operating-cost discipline that underwrites Black Bear underwrites Northern Forge — fuel, variable O&M, maintenance reserve, TIER carbon, and fixed SG&A, in operating-cost basis only.

Phase I energizing Q4 2026 makes Northern Forge the fastest power-and-compute build in the Teton portfolio — first power in months, not years.

Phase All-in $/MWh
Phase I (Q4 2026) <$32
Steady-state, long-term <$30
Reference: Black Bear (Year-1) ~$28

Phase I and long-term figures reflect all-in cash cost of power on a behind-the-meter delivery basis. Excludes capital recovery and equity return; operating-cost basis only. Source: project financial model. Forward-looking; subject to fuel price, regulatory, and operating assumptions.

REGULATORY CONTEXT

Behind-the-meter is the explicit path forward in Alberta.

Under AESO's emerging Phase 2A Large Load Integration framework, Bring-Your-Own-Generation (BYOG) is the explicit path forward for large compute loads. Physically tethering owned generation to compute load lets the operator decouple where power is generated from where compute is sited. The Alberta provincial government is openly supportive of bring-your-own-power data center development.

Northern Forge is designed inside that framework from the ground up — generation, gas supply, fiber, water, and Tier-compatible data hall pads on one site, under one sponsor.