Projects / Northern Forge

Northern Forge

A 200 MW behind-the-meter natural gas generation facility feeding an on-site compute campus. First power roughly six months from publication; Phase I (30 MW) energizing Q1, 2027.

Capacity

200 MW

Phase I online

Q1, 2027

Phase I cost

<$30/MWh

Site

100 acres

OVERVIEW

First power in months, not years.

Northern Forge is a behind-the-meter gas-to-compute campus in Alberta — 200 MW of dedicated generation feeding compute load on the same site, under one sponsor. Phase I (30 MW) energizes Q1, 2027.

Primary reciprocating engine secured (9.8 MW Caterpillar G20CM34, owned outright, OEM-warrantable). 10-year firm gas supply under LOI with a major midstream counterparty; dedicated 6-inch gas pipeline under LOI with a major midstream operator, sized for the full 200 MW build. AESO grid interconnect targeted for 2028 as Year-2 redundancy and secondary revenue.

SPECIFICATIONS

Project specifications.

Generation

200 MW behind-the-meter natural gas generation. Primary engine secured (9.8 MW reciprocating), owned outright, OEM-warrantable

Configuration

Behind-the-meter — generation physically tethered to on-site compute load

Location

Alberta, Canada

Site

Crown lease accepted for the power plant footprint; expansion parcels totaling 100 acres under application within 1 km of the site

Gas Supply

10-year firm gas supply under LOI with a major midstream counterparty

Gas Delivery

Dedicated 6-inch gas pipeline under LOI with a major midstream operator, sized for the full 200 MW build

Grid Optionality

AESO grid interconnect targeted for 2028 as Year-2 redundancy and secondary revenue

Permits

All major permits in hand

Energization

Phase I (30 MW) Q1 2027

Cost economics

<$30/MWh Cost of Power, starting in Phase I

Northern Forge's economics sit comparably to Black Bear's on a behind-the-meter delivery basis, with the same AECO-hub gas advantage and the same Alberta climate / PUE advantage. Phase I starts below $30/MWh

Behind-the-meter delivery bypasses AESO non-energy charges, transmission losses, and most regulated tariffs. The same operating-cost discipline that underwrites Black Bear underwrites Northern Forge — fuel, variable O&M, maintenance reserve, TIER carbon, and fixed SG&A, in operating-cost basis only.

Phase I energizing Q4 2026 makes Northern Forge the fastest power-and-compute build in the Teton portfolio — first power in months, not years.

Phase All-in $/MWh
Phase I (Q1 2027) <$30
Reference: Black Bear (Year-1) ~$25

Long-term figures reflect all-in cash cost of power on a behind-the-meter delivery basis. Excludes capital recovery and equity return; operating-cost basis only. Source: project financial model. Forward-looking; subject to fuel price, regulatory, and operating assumptions.

REGULATORY CONTEXT

Behind-the-meter is the explicit path forward in Alberta.

Under AESO's emerging Phase 2A Large Load Integration framework, Bring-Your-Own-Generation (BYOG) is the explicit path forward for large compute loads. Physically tethering owned generation to compute load lets the operator decouple where power is generated from where compute is sited. The Alberta provincial government is openly supportive of bring-your-own-power data center development.

Northern Forge is designed inside that framework from the ground up — generation, gas supply, fiber, water, and Tier-compatible data hall pads on one site, under one sponsor.