Projects / Black Bear

Black Bear

A fully-permitted 466 MW natural gas combined-cycle plant paired with approximately 2,500 acres of adjacent, Tier-compatible data center land — with a defined pathway to approximately 3 GW across the campus.

Capacity

466 MW

Target energization

Q3 2028

All-in cash cost

~$28/MWh

Pathway

~3 GW

OVERVIEW

A power-and-campus development at scale.

Black Bear pairs 466 MW of combined-cycle gas generation with approximately 2,500 acres of adjacent land permitted and engineered for Tier-compatible data hall development. The site supports a defined pathway to approximately 3 GW — roughly 2 GW behind-the-meter plus 1 GW grid — across the campus.

Sited in an AESO sub-region with the lowest interconnection fee in Alberta ($10K/MW) — a regulator-driven signal that new dispatchable generation is needed in that exact location.

SPECIFICATIONS

Project specifications.

Generation

466 MW natural gas combined-cycle (NGCC).

Campus

~2,500 acres of adjacent, Tier-compatible data center land. Defined pathway to ~3 GW across the site (~2 GW behind-the-meter + ~1 GW grid).

Location

Alberta, Canada. Sited in the AESO sub-region with the lowest interconnection fee in the province ($10K/MW).

Permits — Federal

Fully permitted at the federal level.

Permits — Provincial

Environmental Protection and Enhancement Act (EPEA), Alberta Utilities Commission (AUC), noise and emissions — all in hand.

Indigenous Consultation

Indigenous consultation complete.

Interconnection

AESO Cluster 3 interconnection application submitted April 2026. No material project changes since prior Cluster 1 approval under previous ownership.

Tier Compatibility

Tier 3/4-targeted: redundant power, gas, fiber, and water for 99.982% uptime.

Energization

Target Q3 2028. Approximately 24 months from Final Investment Decision.

Cost transparency

Power cost: $28.05 per MWh, lined out.

Year-1 (2028) total cash operating cost per MWh of generation, on a behind-the-meter delivery basis. Source: Black Bear project financial model. This is the buildup investors and off-takers can audit.

Behind-the-meter delivery bypasses AESO non-energy charges; the grid-scenario equivalent is approximately $30/MWh. Excludes capital recovery and equity return; operating-cost basis only.

The fuel line reflects AECO gas at a heat rate of 5.33. AECO-hub gas has historically traded approximately 40% below NYMEX / Henry Hub. The variable O&M / LTSA line reflects the long-term service agreement attached to the combined-cycle equipment. Net TIER carbon is the post-credit Alberta TIER regulation cost.

Long-term all-in cash cost stays below $40/MWh through the project life, against an Alberta merchant market forecast to roughly double over five years.

Component $/MWh
Fuel (AECO gas at heat rate 5.33) $9.51
Variable O&M / Long-Term Service Agreement (LTSA) $7.00
Major Maintenance Reserve $1.91
Net TIER Carbon $5.00
Fixed SG&A $4.63
Total Year-1 cash cost (behind-the-meter) $28.05

Source: Black Bear project financial model. Excludes capital recovery and equity return; operating-cost basis only. Forward-looking; subject to fuel price, regulatory, and operating assumptions.

Market context

Recent comparable transactions.

Gigawatt-scale buyers are committing to dedicated, behind-the-meter power. Black Bear sits squarely inside that precedent — at a Year-1 cost roughly a quarter of the delivered cost in Virginia.

Year Buyer / Seller Asset Capacity / Term
2024 Microsoft / Constellation Three Mile Island Unit 1 (nuclear restart) 835 MW / 20 yrs
2024 Amazon (AWS) / Talen Susquehanna nuclear (AWS Cumulus campus) 1,920 MW / 17 yrs
2025 Meta / Constellation Clinton Clean Energy Center (nuclear) 1,121 MW / 20 yrs
2024 Google / Kairos Power SMR fleet (advanced reactors) 500 MW / 20+ yrs
2024 AWS / Talen (powered site) Cumulus campus (powered shell sale) 960 MW — $650M

Sources: Microsoft / Constellation press release, September 2024; Talen Energy 8-K and investor presentations, March 2024; Constellation / Meta press release, June 2025; Google / Kairos public announcement, 2024; AWS / Talen Cumulus campus disclosures, 2024.