Projects / Black Bear
Black Bear
A fully-permitted 466 MW natural gas combined-cycle plant paired with approximately 1,500 acres of adjacent, Tier-compatible data center land — with a defined pathway to approximately 3 GW across the campus.
Phase I
466 MW
Target energization
Q3, 2028
Year-1 cash cost
~$24/MWh
Vetted Project Scale
~3 GW
OVERVIEW
Vertically integrated NGCC and data center campus at scale.
Black Bear pairs 466 MW of natural-gas combined-cycle generation with approximately 1,500 acres of adjacent Crown land being developed for Tier-compatible data center use. The site supports a defined pathway to approximately 3 GW — roughly 2 GW behind-the-meter and 1 GW grid-connected — across one or more campuses.
Black Bear sits squarely between Edmonton's growing retail load, Grande Prairie's industrial expansion, and the oil sands — the center of a transmission corridor that needs far more generation than it has. Power demand waiting to connect in the region outpaces new supply by roughly 30%, and Alberta's grid operator assigned the site the lowest connection fee in the province (CAD $10K/MW) — its clearest signal that new dispatchable generation is wanted exactly here.
The power platform
One asset. Three ways to sell power.
Black Bear was developed power-first — a fully permitted 466 MW plant in a generation-short corridor. That permit is now a platform: one asset that can sell power three ways, and energize compute years ahead of the queue.
01 — Merchant
Sell to the grid
Merchant sales into the AESO grid at the forward 2028 pool price (~$54/MWh) — no offtake commitment required.
02 — Behind-the-meter
Power compute on-site
Feed a Tier-compatible data center on the adjacent campus straight from the plant — no grid queue, ramp cap, or curtailment. The shortest path to large-scale energized compute in the province.
03 — Tether anywhere
Pair generation with load anywhere
Under Alberta's bring-your-own-generation rules, Black Bear can power a data center anywhere on the provincial grid — not just one built on-site. Few large projects can.
Energize early
Compute online as early as 2027.
Holding an approved Alberta Utilities Commission (AUC) power-plant permit unlocks bridging — the right to draw grid power to energize data-center load before the plant is complete. Compute can come online as early as 2027, ahead of the plant's own Q3 2028 commercial operation.
2027
Bridge energization — compute online
Q3 2028
Full 466 MW commercial operation
SPECIFICATIONS
Project specifications.
Generation
Phase I: 466 MW natural gas combined-cycle (NGCC) power plant; Defined pathway to ~3 GW across the site (~2 GW behind-the-meter + ~1 GW grid)
Campus
~1,500 acres of adjacent Crown land being developed for Tier-compatible data center use
Location
Alberta, Canada. Sited in the AESO sub-region with the lowest interconnection fee in the province ($10K/MW)
Permits — Federal
Fully permitted at the federal level
Permits — Provincial
Environmental Protection and Enhancement Act (EPEA), Alberta Utilities Commission (AUC), noise and emissions — all in hand.
Carbon & Emissions
High-efficiency combined-cycle generation. Alberta TIER carbon cost fixed through 2040 (May 2026 Canada–Alberta agreement); CO2 enhanced-oil-recovery hub within 5 km.
Indigenous Consultation
Indigenous consultation complete
Interconnection
AESO Cluster 3 interconnection application filed April 2026
Tier Compatibility
Tier 3/4: redundant power, gas, fiber, and water for 99.982%+ uptime.
Energization
Compute online as early as 2027 (bridge). Full 466 MW target Q3 2028 — approximately 24 months from Final Investment Decision.
Cost transparency
Power cost: $23.69 per MWh.
Year-1 (2028) total cash operating cost per MWh of generation, on a behind-the-meter delivery basis. Source: Black Bear project financial model.
Behind-the-meter delivery bypasses AESO non-energy charges; the grid-scenario equivalent is approximately $26/MWh. Excludes capital recovery and equity return; operating-cost basis only.
The cost reflects AECO gas at a heat rate of 5.69 — AECO-hub gas has historically traded approximately 40% below NYMEX / Henry Hub — a long-term service agreement attached to the combined-cycle equipment, and net Alberta TIER carbon that is fixed through 2040 under the May 2026 Canada–Alberta agreement and nets to zero in Year 1.
Year-1 cash cost of ~$24/MWh against a 2028 AESO pool price of ~$54/MWh — a durable, structural cost-of-power advantage. Detailed project economics and returns are shared with qualified partners under NDA.
$23.69
USD per MWh
Year-1 total cash operating cost, behind-the-meter delivery basis. Excludes capital recovery and equity return.
Source: Black Bear project financial model. Forward-looking; subject to fuel price, regulatory, and operating assumptions. AESO pool price forecast: URICA Commodity Forecast, 2028–2031.
Fully permitted.
Years ahead of the queue.
Project-level materials — CIM, financial model, and data room — available to qualified partners under executed NDA.
Capital partners →Dedicated or behind-the-meter power on Black Bear's 466 MW — compute energizable as early as 2027.
Hyperscalers & off-takers →The structural cost edge behind ~$24/MWh power — and why U.S. sites can't match it.
See the thesis →